  1. E1010 While you have been preoccupied dealing with various cost overruns for the past week, a critical path item did not start on time, and you were not informed until it was several days late. What do you tell your project stakeholders?





  2.  Many project managers have seen a graph which shows “Influence of Stakeholders” starting out high and declining as the project progresses. Conversely, it shows the “Cost of Changes” starting out low and increasing as the project progresses. What is the key message a project manager should obtain from this graph?





  3.  Project stakeholders are individuals and organizations that are actively involved in the project or have an interest in it. Which of these is a likely stakeholder?





  4.  The stakeholders of a project typically have:





  5.  A project manager determines that there are 15 communication channels in the project. The number of stakeholders in the project must then be: