surepasspmp.com timer

Please Do not press "Submit" at the end of the exam until you are sure of your responses, as your test will be graded immediately.
You can hover your mouse pointer over to see the question ID. Good luck!


  1. F1143 What are three tools used in Quality Control Process:





  2.  Which is not a tool used in Quality Planning process :





  3.  3 sigma is equal to ______ percentage of fall between two control limits.





  4.  You are the project manager and you meet with your project team to ensure the project is completed with no deviations from the project requirements.This is part of?





  5.  The zero defects concept: