  1. H1082 When your project first started, you had eight stakeholders. There have been changes made to the project and there are now 14 stakeholders. How many communication channels have been added to the project?





  2.  If there are 10 people working on a project, how many total communication channels are there?





  3.  You are working in the US, but have outsourced programming to India and structural engineering to people in Australia. The project doesn't have the budget to bring all the team together, so you will be relying on e-mail, fax, video conference and chat to work together. This is an example of?





  4.  You are managing a project team that is distributed across global locations. You communicate via email on a daily basis and have a telephonic status call once a week. Which of the following statements is valid?





  5.  A project involved team members situated in Arizona, Nebraska, New York and Ireland. Which of the following activities becomes very important in such a team environment?