  1.  Which of the following project management process gets MOST of a project's budget expended?

    A) Project Executing
    B) Project Planning
    C) Project Closing
    D) Project Monitoring

    Your answer=, Correct answer= , Work Sheet:

  2.  You are a project manager of a company and you are assigned to a project that has already been decided to out source. As a project manager, you need to organize a formal bid process and select the vendor for this project. Your senior management is forcing you to select a vendor which has good relation with your senior management. What is the BEST course of action for you?

    A) Follow the formal bid process, and show the senior management about why the favoured vendor is or is not the best choice.
    B) Report to legal department of your company.
    C) Report to your Manager about this.
    D) Get a written permission from your senior management to bypass the formal bid process.

    Your answer=, Correct answer= , Work Sheet:

  3.  Which of the following document can be used to guide all the work in both project executing and project monitoring and controlling phase of a project?

    A) Project Management Plan
    B) Project Risk Plan
    C) Project QA Plan
    D) Project Charter

    Your answer=, Correct answer= , Work Sheet:

  4.  You?re the project manager for an industrial design project. Your team members report to you, and you?re responsible for creating the budget, building the schedule, and assigning the tasks. When the project is complete, you release the team so they can work on other projects for the company. What kind of organization do you work in?

    A) Functional
    B) Weak Matrix
    C) Strong Matrix
    D) Projectized

    Your answer=, Correct answer= , Work Sheet:

  5.  The 2 years project has 200 work packages and a $20,000 budget. After one year, 100 work packages are completed and $10,000 has been spent. Which of the following is TRUE?

    A) The project need 50 work package to be completed in 6 months.
    B) Not enough information available.
    C) The project need 50 work package to be completed in 3 months.
    D) The project is on schedule and on budget.

    Your answer=, Correct answer= , Work Sheet: