4  (80%) -10620 Sec

  1.  Pareto's Law states that eighty percent of the ______ are due to twenty percent of the _______. This is also known as the 80/20 rule.

    A) problems/causes
    B) causes/problems
    C) work/effort
    D) effort/work

    Your answer=B, Correct answer= , Work Sheet:

  2.  You have been asked to establish a project charter for your new project. According to PMBOK, who normally has the responsibility to authorize the charter?

    A) Company president or CEO
    B) Project initiator or sponsor
    C) Key project stakeholders
    D) Project manager

    Your answer=B, Correct answer= , Work Sheet:

  3.  The Project Charter formally authorizes a project. Who authorizes the project charter?

    A) The project manager
    B) A project sponsor or initiator internal to the project organization
    C) The customer
    D) A project sponsor or initiator external to the project organization

    Your answer=D, Correct answer= , Work Sheet:

  4.  In a matrix organization, where the team members report to both, a functional manager as well as a project manager, generally, whose responsibility is it to manage the dual reporting relationship?

    A) Functional manager
    B) HR manager
    C) Team members
    D) Project Manager

    Your answer=D, Correct answer= , Work Sheet:

  5.  A management control point where scope, budget, actual cost and schedule are integrated and compared to earned value for performance measurement is called a:

    A) Code of accounts
    B) Control packages
    C) Control account
    D) Account Plan

    Your answer=C, Correct answer= , Work Sheet: