- Which of these Direct and Manage Project Execution items is not an output of the process?
A) Deliverables
B) Work Performance Information
C) Project management plan
D) Change requests
Your answer=,
Correct answer= ,
Work Sheet:
- What is the difference between the Monitor and Control Project Work process and the Direct and Manage Project Execution process?
A) The Monitor and Control Project Work process and the Direct and Manage Project Execution process are the same.
B) The Monitor and Control Project Work process monitors the project performance while the Direct and Manage Project Execution process is concerned with performing the activities to accomplish project requirements.
C) The Monitor and Control Project Work process is a sub-process of the Direct and Manage Project Execution process.
D) There is no such thing as the Monitor and Control Project Work process.
Your answer=,
Correct answer= ,
Work Sheet:
- Which of these activities would the Close Project or Phase process be applicable to?
A) Cancelled projects
B) Completed projects
C) Completed phases in a multi-phase project
D) All of the above
Your answer=,
Correct answer= ,
Work Sheet:
- The project management team has determined that there some changes to the Scope of the project. Who would be responsible for reviewing, evaluating and approving documented changes to the project?
A) Change Control Board (CCB)
B) Change Configuration Board (CCB)
C) Scope Control Board (SCB)
D) Configuration Control Board (CCB)
Your answer=,
Correct answer= ,
Work Sheet:
- Which process is concerned with providing forecasts to update current cost information?
A) Monitor and Control Project Work
B) Project Management Information System
C) Close Project or Phase
D) Direct and Manage Project Execution
Your answer=,
Correct answer= ,
Work Sheet: