- A control chart should always contain:
A) Upper and lower warning limits
B) The cumulative average
C) Upper and lower control limits
D) A target value
Your answer=,
Correct answer= ,
Work Sheet:
- Which of the following statements is correct?
A) A collection of unrelated programs can constitute a portfolio.
B) The scope of a portfolio is typically smaller than that of a program.
C) A program is a group of unrelated projects.
D) A program need not consist of projects.
Your answer=,
Correct answer= ,
Work Sheet:
- Which of the following is not a general management technique used to generate different approaches to execute and perform the project work?
A) Lateral thinking
B) Six Thinking Hats
C) Map Out
D) Brainstorming
Your answer=,
Correct answer= ,
Work Sheet:
- If you want to compress a project schedule, what are two of the recommended alternatives to consider?
A) Fast Tracking and Schedule Network Analysis
B) Crashing and Fast Tracking
C) Resource Leveling and What-If Scenario Analysis
D) Crashing and Schedule Network Analysis
Your answer=,
Correct answer= ,
Work Sheet:
- Which tools and techniques are recommended for developing a project team?
A) Performance assessment, recognition and rewards, and team building
B) Training, team building, and ground rules
C) Team building, creating organizational charts, and assessing individual's performance
D) Setting ground rules and assessing team members based on those rules
Your answer=,
Correct answer= ,
Work Sheet: