- At the end of a project, what will your schedule variance be equal to?
A) Zero
B) Five
C) One
D) Hundred
Your answer=A,
Correct answer= ,
Work Sheet:
- A control chart should always contain:
A) Upper and lower warning limits
B) The cumulative average
C) Upper and lower control limits
D) A target value
Your answer=C,
Correct answer= ,
Work Sheet:
- As a project manager, you are responsible for determining and delivering the required levels of both grade and quality. Select which of the following statements you disagree with.
A) A product can be of a low quality but high grade.
B) Low quality and Low grade are always a problem.
C) A product can be of a high quality but low grade.
D) Low quality is always a problem but low grade need not always be a problem.
Your answer=D,
Correct answer= ,
Work Sheet:
- Which of these statement correctly links project and product life cycles?
A) A product life cycle is generally contained within a project life cycle.
B) A project life cycle is generally contained within a product life cycle.
C) A product life cycle is the same as a project life cycle.
D) The last life cycle for a project is generally the product's retirement.
Your answer=B,
Correct answer= ,
Work Sheet:
- The Project Charter formally authorizes a project. Who authorizes the project charter?
A) The project manager
B) A project sponsor or initiator internal to the project organization
C) The customer
D) A project sponsor or initiator external to the project organization
Your answer=D,
Correct answer= ,
Work Sheet: