- What is the difference between the Monitor and Control Project Work process and the Direct and Manage Project Execution process?
A) The Monitor and Control Project Work process and the Direct and Manage Project Execution process are the same.
B) The Monitor and Control Project Work process monitors the project performance while the Direct and Manage Project Execution process is concerned with performing the activities to accomplish project requirements.
C) The Monitor and Control Project Work process is a sub-process of the Direct and Manage Project Execution process.
D) There is no such thing as the Monitor and Control Project Work process.
Your answer=D,
Correct answer= ,
Work Sheet:
- Which process is concerned with providing forecasts to update current cost information?
A) Monitor and Control Project Work
B) Project Management Information System
C) Close Project or Phase
D) Direct and Manage Project Execution
Your answer=A,
Correct answer= ,
Work Sheet:
- Which of the following would not be considered as an Enterprise Environmental Factor during the Develop Project Charter process?
A) Scope Statement
B) Organizational infrastructure
C) Governmental standards
D) Marketplace conditions
Your answer=B,
Correct answer= ,
Work Sheet:
- Which of these Direct and Manage Project Execution items is not an output of the process?
A) Deliverables
B) Work Performance Information
C) Project management plan
D) Change requests
Your answer=A,
Correct answer= ,
Work Sheet:
- The project manager of a project calls you in as a consultant to provide inputs on developing the Project Charter. Your contribution to the project could be best termed as:
A) Professional Consultant
B) Expert Judgment
C) Charter Consultant
D) Expert Consultancy
Your answer=A,
Correct answer= ,