- Which of these activities would the Close Project or Phase process be applicable to?
A) Cancelled projects
B) Completed projects
C) Completed phases in a multi-phase project
D) All of the above
Your answer=,
Correct answer= ,
Work Sheet:
- Which of the following would not be considered as an Enterprise Environmental Factor during the Develop Project Charter process?
A) Scope Statement
B) Organizational infrastructure
C) Governmental standards
D) Marketplace conditions
Your answer=,
Correct answer= ,
Work Sheet:
- Which of these tools and techniques are common to all six Project Integration Management processes?
A) Project management Information System
B) Earned value technique
C) Project management methodology
D) Expert Judgment
Your answer=,
Correct answer= ,
Work Sheet:
- The project management team has determined that there some changes to the Scope of the project. Who would be responsible for reviewing, evaluating and approving documented changes to the project?
A) Change Control Board (CCB)
B) Change Configuration Board (CCB)
C) Scope Control Board (SCB)
D) Configuration Control Board (CCB)
Your answer=,
Correct answer= ,
Work Sheet:
- What is the difference between the Monitor and Control Project Work process and the Direct and Manage Project Execution process?
A) The Monitor and Control Project Work process and the Direct and Manage Project Execution process are the same.
B) The Monitor and Control Project Work process monitors the project performance while the Direct and Manage Project Execution process is concerned with performing the activities to accomplish project requirements.
C) The Monitor and Control Project Work process is a sub-process of the Direct and Manage Project Execution process.
D) There is no such thing as the Monitor and Control Project Work process.
Your answer=,
Correct answer= ,
Work Sheet: