A management control point where scope, budget, actual cost and schedule are integrated and compared to earned value for performance measurement is called a:
A) Code of accounts
B) Control packages
C) Control account
D) Account Plan
Your answer=C,
Correct answer=
,
Work Sheet:
A control chart should always contain:
A) Upper and lower warning limits
B) The cumulative average
C) Upper and lower control limits
D) A target value
Your answer=C,
Correct answer=
,
Work Sheet:
Which of the following is not a general management technique used to generate different approaches to execute and perform the project work?
A) Lateral thinking
B) Six Thinking Hats
C) Map Out
D) Brainstorming
Your answer=C,
Correct answer=
,
Work Sheet:
Which of these statement correctly links project and product life cycles?
A) A product life cycle is generally contained within a project life cycle.
B) A project life cycle is generally contained within a product life cycle.
C) A product life cycle is the same as a project life cycle.
D) The last life cycle for a project is generally the product's retirement.
Your answer=B,
Correct answer=
,
Work Sheet:
If you want to compress a project schedule, what are two of the recommended alternatives to consider?
A) Fast Tracking and Schedule Network Analysis
B) Crashing and Fast Tracking
C) Resource Leveling and What-If Scenario Analysis
D) Crashing and Schedule Network Analysis
Your answer=B,
Correct answer=
,
Work Sheet: