  1.  Which of these statement correctly links project and product life cycles?

    A) A product life cycle is generally contained within a project life cycle.
    B) A project life cycle is generally contained within a product life cycle.
    C) A product life cycle is the same as a project life cycle.
    D) The last life cycle for a project is generally the product's retirement.

    Your answer=, Correct answer= , Work Sheet:

  2.  As a project manager, you are responsible for determining and delivering the required levels of both grade and quality. Select which of the following statements you disagree with.

    A) A product can be of a low quality but high grade.
    B) Low quality and Low grade are always a problem.
    C) A product can be of a high quality but low grade.
    D) Low quality is always a problem but low grade need not always be a problem.

    Your answer=, Correct answer= , Work Sheet:

  3.  During a weekly staff meeting another project manager, a certified PMP, is reporting that a project he is running completed successfully the night before. However, you know that there are still several large outstanding deliverables. What do you do?

    A) File a complaint with PMI.
    B) Notify the project manager's supervisor, and file a complaint with PMI.
    C) Do nothing.
    D) Notify the project manager's supervisor.

    Your answer=, Correct answer= , Work Sheet:

  4.  Which of the following is not a general management technique used to generate different approaches to execute and perform the project work?

    A) Lateral thinking
    B) Six Thinking Hats
    C) Map Out
    D) Brainstorming

    Your answer=, Correct answer= , Work Sheet:

  5.  Which of the following statements is correct?

    A) A collection of unrelated programs can constitute a portfolio.
    B) The scope of a portfolio is typically smaller than that of a program.
    C) A program is a group of unrelated projects.
    D) A program need not consist of projects.

    Your answer=, Correct answer= , Work Sheet: