Please review your test results by moving cursor to answer sheet icon.


  1.  

    A)
    B)
    C)
    D)

    Your answer=, Correct answer= ,

  2.  A hierarchical structure of resources organized by resource type category and resource type used in resource leveling schedules is known as:

    A) Team structure
    B) Resource Pool
    C) Organization breakdown Structure
    D) Resource Breakdown Structure

    Your answer=A, Correct answer= , Work Sheet:

  3.  A ______ is a collection of projects or programs grouped together for strategic business needs.

    A) Portfolio
    B) Management System
    C) Enterprise
    D) Array

    Your answer=C, Correct answer= , Work Sheet:

  4.  

    A)
    B)
    C)
    D)

    Your answer=, Correct answer= ,

  5.  Which of the following inaccurately describes a prototype?

    A) A prototype is tangible and allows stakeholders to fine-tune their expectations.
    B) Requirements from a prototype are usually insufficient to move to the design phase.
    C) Prototypes support the concept of progressive elaboration.
    D) A prototype is a working model of the expected product.

    Your answer=A, Correct answer= , Work Sheet: