A)
B)
C)
D)
Your answer=,
Correct answer= ,
- Which of these Direct and Manage Project Execution items is not an output of the process?
A) Deliverables
B) Work Performance Information
C) Project management plan
D) Change requests
Your answer=A,
Correct answer= ,
Work Sheet:
-
A)
B)
C)
D)
Your answer=,
Correct answer= ,
- The project manager of a project calls you in as a consultant to provide inputs on developing the Project Charter. Your contribution to the project could be best termed as:
A) Professional Consultant
B) Expert Judgment
C) Charter Consultant
D) Expert Consultancy
Your answer=C,
Correct answer= ,
Work Sheet:
-
A)
B)
C)
D)
Your answer=,
Correct answer= ,