- If you want to compress a project schedule, what are two of the recommended alternatives to consider?
A) Fast Tracking and Schedule Network Analysis
B) Crashing and Fast Tracking
C) Resource Leveling and What-If Scenario Analysis
D) Crashing and Schedule Network Analysis
Your answer=A,
Correct answer= ,